Construction of Flood Mitigation Structure23F00084

Construction of Agos River - Bato - Lake Flood Control, Sta. Cruz - San Vicente, Bato, Section, Bato, Camarines Sur

Construction of Agos River - Bato - Lake Flood Control, Sta. Cruz - San Vicente, Bato, Section, Bato, Camarines Sur is a DPWH-tracked public work in BATO (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱121,061,136.60. Status: Reported complete (DPWH). Contractor on record: BICOL GOLDROCK CONST CORP. Figures trace to sumbong.

BATO (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Roque-Li±aga Creek Flood Control, Canaman, Camarines Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Camarines Sur 5th District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱121,061,136.60

Progress

Reported complete (DPWH)

Start Date

March 27, 2023

Target End

April 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.