Construction of Flood Mitigation Structure22DI0023

Construction of River Protection Structure along San Cristobal River, (near Looc Bridge), Brgy. Looc, Calamba City, Laguna

Construction of River Protection Structure along San Cristobal River, (near Looc Bridge), Brgy. Looc, Calamba City, Laguna is a DPWH-tracked public work in CITY OF CALAMBA (LAGUNA), LAGUNA, Region IV-A. Reported contract value: ₱80,693,065.75. Status: Reported complete (DPWH). Contractor on record: ST GERRARD CONST GEN CONTRACTOR & DEVELOPMENT CORP FORMERLY:ST GERRARD CONST. Figures trace to sumbong.

CITY OF CALAMBA (LAGUNA), LAGUNA, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment/Floodwall at Brgy. Bi±an, Bi±an City, Laguna
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002907

₱1,026,969,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003022

₱159,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-22-0007547

₱51,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002753

₱40,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

CONSTRUCTION OF THE NBI MAIN BUILDING (PHASE I)

National Capital Region, National Capital Region

2023₱447.7M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURES AL;ONG PUERTO PRINCESA SDOUTH ROAD, K0147+398-K0180+313 (WITH EXCEPTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SPECIAL ROAD FUND- MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239- INSTALLATION OF ROADWAY LIGHTING STRUCTURE ALONG PUERTO PRINCESA SOUTH ROAD- K0180+313-K0203+730 (INTERMITTENT SECTIONS), PALAWAN

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, PRIMARY ROADS, DAANG MAHARLIKA (LZ), NUEVA ECIJA 2ND LEGISLATIVE DISTRICT, PROVINCE OF NUEVA ECIJA

Region III, Region III

2017₱289.5M
Reported complete (DPWH)
No sat.

CLUSTER 1: 1. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF PALO - PASTRANA - STA. FE BY-PASS RD, PACKAGE A 2. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATION

Region VIII, Region VIII

2025₱289.4M
Ongoing (DPWH-reported)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: CONSTRUCTION OF MISSING LINKS/NEW ROADS -TUGUEGARAO CITY BOULEVARD (PINACANAUAN BRIDGE 2 AND APPROACHES), PHASE 2

Region II, Region II

2023₱285.9M
Past target date (DPWH On-Going)
View all 103 projects →

4. Implementation

Contract Amount

₱80,693,065.75

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

February 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.