Construction of Flood Mitigation Structure22FF0049

Construction/Rehabilitation/Improvement of Flood Mitigation Structure, Bicol River Flood Control, Brgy. Barobaybay (Barobaybay Section - Left Side), Magarao, Camarines Sur

Construction/Rehabilitation/Improvement of Flood Mitigation Structure, Bicol River Flood Control, Brgy. Barobaybay (Barobaybay Section - Left Side), Magarao, Camarines Sur is a DPWH-tracked public work in MAGARAO (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱67,323,312.63. Status: Reported complete (DPWH). Contractor on record: PRECIOUS CONST. Figures trace to sumbong.

MAGARAO (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation/Improvement of Flood Mitigation Structure, Bicol River Flood Control, Brgy. Tabuco (Tabuco Section - Left Side), Naga City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003136

₱361,387,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003056

₱75,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003046

₱14,500,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱67,323,312.63

Progress

Reported complete (DPWH)

Start Date

May 24, 2022

Target End

March 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.