Flood Control and Drainage25OB0131

CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER LAKESHORE AREA (PHASE 3), TAGUIG CITY

CONSTRUCTION OF SLOPE PROTECTION ALONG TAGUIG RIVER LAKESHORE AREA (PHASE 3), TAGUIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱94,565,100.20. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TOUGHBUILT CONST. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱60,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Casili Creek, Caloocan City (Phase 2)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

67 projects · ₱2.2B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG POLO RIVER (PHASE 17), VALENZUELA CITY

Metro Manila 3rd DEO, National Capital Region

2025₱142.1M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES: CONSTRUCTION OF BANICA RIVER CONTROL, BRGY. BALUGO, DUMAGUETE CITY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2023₱99.0M
Past target date (DPWH On-Going)

BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES: CONSTRUCTION OF BANICA RIVER CONTROL , BRGY. CANDAU-AY, DUMAGUETE CITY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2023₱99.0M
Reported complete (DPWH)

BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES: CONSTRUCTION OF BANICA RIVER CONTROL, BRGY. CADAWINONAN, DUMAGUETE CITY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2023₱99.0M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF RIVER CONTROL AT STA. CRUZ VIEJO, TANJAY CITY, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2023₱96.5M
Reported complete (DPWH)

CONSTRUCTION OF RIVER CONTROL SYSTEM AND REHABILITATION OF WATERWAYS ALONG BALAGTAS RIVER BRGY. SAN JUAN BALAGTAS, BULACAN (STA. 14+577 TO STA. 14+781)

Bulacan 1st DEO, Region III

2023₱96.5M
Reported complete (DPWH)
View all 67 projects →

4. Implementation

Contract Amount

₱94,565,100.20

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 18, 2025

Target End

October 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.