Flood Control and Drainage18IA0003

CONST./EXTENSION OF FLOOD CONTROL STRUCTURE ALONG ANAS RIVER (PHASE 3) PROTECTING ANAS BRIDGE & BILIRAN CIRCUMFERENTIAL ROAD, UPSTREAM RIGHTSIDE (11.5733, 124.4034); UPSTREAM LEFTSIDE (11.5742, 124.4027), ANAS, PROVINCE OF BILIRAN

CONST./EXTENSION OF FLOOD CONTROL STRUCTURE ALONG ANAS RIVER (PHASE 3) PROTECTING ANAS BRIDGE & BILIRAN CIRCUMFERENTIAL ROAD, UPSTREAM RIGHTSIDE (11.5733, 124.4034); UPSTREAM LEFTSIDE (11.5742, 124.4027), ANAS, PROVINCE OF BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱27,730,000.00. Status: Reported complete (DPWH). Contractor on record: YOYEN ENT. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Extension of Flood Control Structure along Anas River (Phase 3) protecting Anas Bridge and Biliran Circumferential Road, Naval, Biliran
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-18-0024228

₱11,034,798.00 · FY2018

Source

3. Procurement & Award

Confirmed (exact contract ID) · 100%

18IA0003 Construction/Extension of Flood Control S

₱27,730,000.00 · YOYEN ENTERPRISES

Contractor

72 projects · ₱1.5B total · 3 flags

Other projects by this contractor

View all 72 projects →

4. Implementation

Contract Amount

₱27,730,000.00

Progress

Reported complete (DPWH)

Start Date

February 18, 2018

Target End

July 17, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.