Flood Control and Drainage20FO0011

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG QUINALE RIVER (UPSTREAM OF BUSAC BRIDGE) (BUSAC SECTION), OAS, ALBAY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG QUINALE RIVER (UPSTREAM OF BUSAC BRIDGE) (BUSAC SECTION), OAS, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱16,746,501.05. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: BAM CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱18,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Quinale River (Upstream of Busac Bridge) (Busac Section), Oas, Albay
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Albay 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱16,746,501.05

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 17, 2020

Target End

August 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.