Flood Control and Drainage25CC0330

CONSTRUCTION OF PUMPING STATION AND FLOOD GATE AT CALERO CREEK, PHASE II, MALOLOS CITY, BULACAN

CONSTRUCTION OF PUMPING STATION AND FLOOD GATE AT CALERO CREEK, PHASE II, MALOLOS CITY, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱92,459,769.17. Status: Past target date (DPWH On-Going). Contractor on record: M S RAMOS CONST INC FORMERLY: M S RAMOS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱45,000

    Probable match · score 0.88

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱92,459,769 · M.S. RAMOS CONSTRUCTION .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    0% reported · imagery 2019-10-05 → 2025-04-07

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Pumping station, cost per station (new construction)

₱92,459,769 per station= 1.0x the Region III median (n=33)

Contract cost ₱92,459,769 ÷ 1 station read from the DPWH title (“PUMPING STATION”; single new pumping station named in title). National percentile: 66. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Bulacan

Based on the coordinates published with the DPWH record and NOAH file Bulacan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF PUMPING STATION AND FLOOD GATE AT CALERO CREEK, PHASE II, MALOLOS CITY, BULACAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure with Pumping Station and Flood Gate at Mambog Creek, Malolos City, Bulacan (Phase III)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

25CC0330-Construction of Pumping Station and Flood

₱92,459,769.17 · M.S. RAMOS CONSTRUCTION .

Contractor

B

163 projects · ₱5.1B total · 1 flags

4. Implementation

Contract Amount

₱92,459,769.17

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

December 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)BulacanCity of MalolosCalero
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Man-Yi 2024Trami 2024
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.