Construction of Flood Mitigation Structure21GA0101

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Sta. Cruz - Bigaa, Lezo, Aklan

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Sta. Cruz - Bigaa, Lezo, Aklan is a DPWH-tracked public work in AKLAN, Region VI. Reported contract value: ₱93,520,048.17. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST & SUPPLY INC FORMERLY: ADP CONST & SUPPLY. Figures trace to sumbong.

AKLAN, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱19,250,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aklan River, Tigayon, Kalibo, Aklan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008634

₱109,500,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008988

₱55,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008590

₱18,700,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007611

₱11,500,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,520,048.17

Progress

Reported complete (DPWH)

Start Date

April 15, 2021

Target End

February 24, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.