Rehabilitation / Major Repair of Drainage Structure23OB0088

Rehabilitation of Flood Control Structure along Buli Creek, Pasig City Phase II

Rehabilitation of Flood Control Structure along Buli Creek, Pasig City Phase II is a DPWH-tracked public work in CITY OF PASIG (METROPOLITAN MANILA), PASIG CITY, National Capital Region. Reported contract value: ₱46,535,105.00. Status: Reported complete (DPWH). Contractor on record: DAHL CONST CORP FORMERLY: DAHL CONST. Figures trace to sumbong.

CITY OF PASIG (METROPOLITAN MANILA), PASIG CITY, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Buli Creek, Pasig City Phase II
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Metro Manila 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱46,535,105.00

Progress

Reported complete (DPWH)

Start Date

February 6, 2023

Target End

October 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.