Flood Control and Drainage21FA0013

REHABILITATION/IMPROVEMENT OF BULAWAN FLOOD CONTROL, SAN FRANCISCO SECTION, MALILIPOT, ALBAY

REHABILITATION/IMPROVEMENT OF BULAWAN FLOOD CONTROL, SAN FRANCISCO SECTION, MALILIPOT, ALBAY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱55,970,000.00. Status: Reported complete (DPWH). Contractor on record: 3DIAMONDS CONST CORP. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱39,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱54,119,907 · 3DIAMONDS CONST CORP

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-09-05 → 2025-10-05

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Albay

Based on the coordinates published with the DPWH record and NOAH file Albay.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION/IMPROVEMENT OF BULAWAN FLOOD CONTROL, SAN FRANCISCO SECTION, MALILIPOT, ALBAY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱39,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of San Rafael Flood Control, Guinobatan, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Contract ID No. 21FA0013

₱54,119,906.66 · 3DIAMONDS CONST CORP

Award / contract ref: 21FA0013

Contractor

C

69 projects · ₱3.1B total · 0 flags

Other projects by this contractor

Construction/Improvement/Rehabilitation of Nasisi River Flood Mitigation Structure (Barangay Batang, Barangay Herrera, and Barangay Pinit), Ligao City, Albay

CITY OF LIGAO (ALBAY), ALBAY, Region V

2023₱115.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0505+419-K0505+600, K0509+704-K0510+912, GUINOBATAN, ALBAY (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2025₱100.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM(BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF SAN FRANCISCO RIVER FLOOD MITIGATION STRUCTURES, BRGY. MAGUIRON AND BRGY. M

Albay 3rd DEO, Region V

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER V-2022: 1.) REHABILITATION OF TANDARORA FLOOD CONTROL DIKE (LEFT SIDE) GUINOBATAN, ALBAY; AND 2.) REHABILITATION OF TANDARORA FLOOD CONTROL DIKE (RIGHT SIDE) GUINOBATAN, ALBAY

Albay 3rd DEO, Region V

2022₱98.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF NASISI RIVER FLOOD MITIGATION STRUCTURE, BARANGAY NABONTON, LIGAO CITY, ALBAY

Albay 3rd DEO, Region V

2024₱96.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION RIVERBANK CONTROL STRUCTURE ALON

Albay 3rd DEO, Region V

2025₱94.1M
Past target date (DPWH On-Going)
View all 69 projects →

4. Implementation

Contract Amount

₱55,970,000.00

Progress

Reported complete (DPWH)

Start Date

March 19, 2021

Target End

November 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)AlbayMalilipotSan Jose
Storms whose wind field reached it
Nokaen 2026Fung-Wong 2025Fengshen 2025Bualoi 2025Man-Yi 2024
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.