Construction of Flood Mitigation Structure21D00079

Construction of slope protection, road and other improvements along river in Molino III and Barangay Molino VI, Bacoor City, Cavite

Construction of slope protection, road and other improvements along river in Molino III and Barangay Molino VI, Bacoor City, Cavite is a DPWH-tracked public work in CAVITE, Region IV-A. Reported contract value: ₱244,114,309.50. Status: Reported complete (DPWH). Contractor on record: E F CHUA CONST INC. Figures trace to sumbong.

CAVITE, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures and Drainage Systems along Bacoor-Dasmari±as Road K0022 + 220 - K0023 + 920 with exceptions, Bacoor City, Cavite
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Cavite 3rd District Engineering Office · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱244,114,309.50

Progress

Reported complete (DPWH)

Start Date

December 3, 2021

Target End

September 28, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.