Flood Control and Drainage24F00265

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BASUD RIVER FLOOD MITIGATION STR

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BASUD RIVER FLOOD MITIGATION STR is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱173,699,778.33. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: TR CONST CORP FOR: TR CONST. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱173,699,778.33

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 3, 2024

Target End

March 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.