Construction of Flood Mitigation Structure23F00040

Construction of Road Dike along Hitoma River, Phase I, Barangay Obi, Caramoran, Catanduanes

Construction of Road Dike along Hitoma River, Phase I, Barangay Obi, Caramoran, Catanduanes is a DPWH-tracked public work in CARAMORAN (CATANDUANES), CATANDUANES, Region V. Reported contract value: ₱192,961,477.80. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST & DEVELOPMENT CORP. Figures trace to sumbong.

CARAMORAN (CATANDUANES), CATANDUANES, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures, Barangay Tilod, Baras, Catanduanes
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Catanduanes District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

107 projects · ₱14.4B total · 65 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF CRUISE PORT AND FACILITIES PACKAGE 3, LEGAZPI CITY, LEGAZPI CITY, ALBAY (2ND LEGISLATIVE DISTRICT

Region V, Region V

2024₱391.8M
Past target date (DPWH On-Going)
No sat.

SIPAG - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF CAUSEWAY, SECTION 3.14A, TACLOBAN CITY, LEYTE

Region VIII, Region VIII

2025₱313.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF COASTAL ROAD, BARANGAY POBLACION, RAPU-RAPU, ALBAY, RAPU-RAPU, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱292.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY MOROCBOROCAN TO BARANGAY POBLACION, R

Region V, Region V

2024₱291.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIP[AG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MAG-ASAWANG TUBIG RIVER, BRGY. INARAWAN, PHASE I, NAUJAN, ORIENTAL MINDORO

Region IV-B, Region IV-B

2024₱279.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, MAGALLANG-MOROPONROS, LIBON/OAS, ALBAY (PHASE

Region V, Region V

2024₱244.8M
Past target date (DPWH On-Going)
View all 107 projects →

4. Implementation

Contract Amount

₱192,961,477.80

Progress

Reported complete (DPWH)

Start Date

March 27, 2023

Target End

March 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.