Flood Control and Drainage18EA0062

CONSTRUCTION OF CONCRETE DIKE FLOOD CONTROL STRUCTURE ALONG BOAC RIVER AT BRGY. SANTOL-MURALLON SECT

CONSTRUCTION OF CONCRETE DIKE FLOOD CONTROL STRUCTURE ALONG BOAC RIVER AT BRGY. SANTOL-MURALLON SECT is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱57,040,352.77. Status: Reported complete (DPWH). Contractor on record: J D LEGASPI CONST. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱57,040,352.77

Progress

Reported complete (DPWH)

Start Date

March 1, 2018

Target End

June 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.