Construction of Flood Mitigation Structure22BI0036

Construction of Homestead Flood Control Structure along Sta. Fe River, Bambang, Nueva Vizcaya

Construction of Homestead Flood Control Structure along Sta. Fe River, Bambang, Nueva Vizcaya is a DPWH-tracked public work in BAMBANG (NUEVA VIZCAYA), NUEVA VIZCAYA, Region II. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: BRG CONST. Figures trace to sumbong.

BAMBANG (NUEVA VIZCAYA), NUEVA VIZCAYA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Homestead Flood Control Structure along Sta. Fe River, Bambang, Nueva Vizcaya
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0011002

₱75,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002786

₱33,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002432

₱21,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002996

₱409,500,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0002544

₱310,863.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0002545

₱27,137.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0008154

₱5,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

85 projects · ₱2.5B total · 1 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 10, 2022

Target End

December 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.