Construction of Flood Mitigation Structure23DB0090

Construction of Flood Control Structure along Pansipit River, Lemery, Batangas

Construction of Flood Control Structure along Pansipit River, Lemery, Batangas is a DPWH-tracked public work in LEMERY (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: 515 LIFE CONST CORP / V R PATRON BUILDERS & DEVELOPERS CORP PREVIOUSL. Figures trace to sumbong.

LEMERY (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Calumpang River (Section 5), Batangas City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

June 15, 2023

Target End

April 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.