Construction of Flood Mitigation Structure22OI0049

Construction of Flood Control Structure along Laguna de Bay, Barangay Putatan, Muntinlupa City

Construction of Flood Control Structure along Laguna de Bay, Barangay Putatan, Muntinlupa City is a DPWH-tracked public work in CITY OF MUNTINLUPA (METROPOLITAN MANILA), MUNTINLUPA CITY, National Capital Region. Reported contract value: ₱91,568,484.81. Status: Reported complete (DPWH). Contractor on record: E F CHUA CONST INC. Figures trace to sumbong.

CITY OF MUNTINLUPA (METROPOLITAN MANILA), MUNTINLUPA CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure, Barangay Buli, Muntinlupa City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003114

₱1,023,303,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003031

₱10,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0006102

₱2,820,484.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0006103

₱263,928.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱91,568,484.81

Progress

Reported complete (DPWH)

Start Date

February 17, 2022

Target End

August 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.