Construction of Flood Mitigation Structure23CJ0009

Construction of Camiling River Left Bank, Anoling 3rd to Pao 1st Section Package B, Camiling, Tarlac

Construction of Camiling River Left Bank, Anoling 3rd to Pao 1st Section Package B, Camiling, Tarlac is a DPWH-tracked public work in CAMILING (TARLAC), TARLAC, Region III. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: ROYAL CROWN MONARCH CONST & SUPPLIES CORP. Figures trace to sumbong.

CAMILING (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Tarlac District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

February 10, 2023

Target End

October 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.