Flood Control and Drainage19OE0041

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM, CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE FEEDER LINES CONNECTING TO BLUMENTRITT INTERC

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM, CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE FEEDER LINES CONNECTING TO BLUMENTRITT INTERC is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱31,846,963.50. Status: Reported complete (DPWH). Contractor on record: EL-JAKE BUILDERS. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-BMB-A-19-0005535 · ₱3,306,000 · release to the district office, not itemized per project

    Possible match · score 0.76

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19OE0041 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-05-26 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · NCR, City of Manila, First District

Based on the coordinates published with the DPWH record and NOAH file Metro Manila.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM, CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE FEEDER LINES CONNECTING TO BLUMENTRITT INTERC

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0005535

₱3,306,000.00 · FY2019

Released to Regional Office - XI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

117 projects · ₱1.9B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONST/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMSCONST OF FLOOD CONTROL STRUCTURE ALONG KALERO RIVER, BRGY. SAN RAFAEL, NOVELETA, CAV

Cavite 1st DEO, Region IV-A

2024₱100.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG YLANG-YLANG RIVER, BARANGAY SANTA ISABEL,KAWIT

Cavite 1st DEO, Region IV-A

2024₱95.5M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF MULTI-PURPOSE BUILDING WITHIN ZONE 58 TO 67, MANILA CITY (PHASE III)

North Manila DEO, National Capital Region

2025₱78.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN TO BOSO-BOSO RIVER (DOWNSTREAM PHASE 2), K0035+900 ALONG MARIKINA-INFANTA ROAD ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2020₱55.0M
Reported complete (DPWH)
No sat.

IMPROVEMENT/CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN RIVER (UPSTREAM PHASE 7), K0035+900 ALONG MARIKINA-INFANTA ROAD, ANTIPOLO CITY (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2019₱55.0M
Reported complete (DPWH)
No sat.

Construction of Flood Control and Slope Protection Structure along Upper Marikina River, Barangay San Jose, Rodriguez, Rizal

MONTALBAN (RIZAL), RIZAL, Region IV-A

2023₱48.2M
Reported complete (DPWH)
View all 117 projects →

4. Implementation

Contract Amount

₱31,846,963.50

Progress

Reported complete (DPWH)

Start Date

June 6, 2019

Target End

January 31, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of ManilaSanta CruzBarangay 372
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Man-Yi 2024Trami 2024
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.