Construction of Flood Mitigation Structure24IC0064

Construction of Flood Control along Binahaan River, Barangay Camire, Tanauan, Leyte

Construction of Flood Control along Binahaan River, Barangay Camire, Tanauan, Leyte is a DPWH-tracked public work in TANAUAN (LEYTE), LEYTE, Region VIII. Reported contract value: ₱96,450,000.44. Status: Reported complete (DPWH). Contractor on record: EZJONES CONST INC / XDR CONST AND SUPPLY. Figures trace to sumbong.

TANAUAN (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Lingayon River, Barangay Lingayon, Alangalang, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008481

₱1,388,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008493

₱128,000.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱96.5M total · 0 flags

4. Implementation

Contract Amount

₱96,450,000.44

Progress

Reported complete (DPWH)

Start Date

February 15, 2024

Target End

November 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.