Construction of Flood Mitigation Structure23OE0198

Construction of Retarding Basin at Brgy 129, Vitas, Tondo, Manila

Construction of Retarding Basin at Brgy 129, Vitas, Tondo, Manila is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱41,576,933.09. Status: Reported complete (DPWH). Contractor on record: JELSIE CONST & SUPPLY. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,343,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure, Easement Road Estero de Pandacan (Tripa de Gallina - P. Quirino Ave.) Manila
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

North Manila District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Projects

₱40,509,967.63 · JELSIE CONSTRUCTION & SUPPLY

4. Implementation

Contract Amount

₱41,576,933.09

Progress

Reported complete (DPWH)

Start Date

March 20, 2023

Target End

September 29, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.