Construction of Flood Mitigation Structure22DH0069

Bank Improvement along Santa Cruz River, Pagsanjan Section, Pagsanjan, Laguna

Bank Improvement along Santa Cruz River, Pagsanjan Section, Pagsanjan, Laguna is a DPWH-tracked public work in PAGSANJAN (LAGUNA), LAGUNA, Region IV-A. Reported contract value: ₱93,604,490.24. Status: Reported complete (DPWH). Contractor on record: JTC CRUZ CONST CO INC. Figures trace to sumbong.

PAGSANJAN (LAGUNA), LAGUNA, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment/Floodwall (Staggered), Bi±an City, Laguna
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002906

₱322,200,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-22-0007482

₱25,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

154 projects · ₱8.5B total · 5 flags

4. Implementation

Contract Amount

₱93,604,490.24

Progress

Reported complete (DPWH)

Start Date

September 9, 2022

Target End

August 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.