- C5 · Pattern Consistent with Contract SplittingConstruction of Dicamay1 Flood Control Structure Section 2 Jones, IsabelaDPWH project · contractor Danysons Const and Development Corp Formerly: Danysons Const
- C5 · Pattern Consistent with Contract SplittingConstruction of Dicamay1 Flood Control Structure Section 1 Jones, IsabelaDPWH project · contractor Danysons Const and Development Corp Formerly: Danysons Const
- C7 · High Concurrent Workload for One ContractorSt Gerrard Const Gen Contractor & Development Corp Formerly:St Gerrard ConstContractor (applies to all its work) · contractor St Gerrard Const Gen Contractor & Development Corp Formerly:St Gerrard Const
- C7 · High Concurrent Workload for One ContractorV B Manubay ConstContractor (applies to all its work) · contractor V B Manubay Const
- C7 · High Concurrent Workload for One ContractorDalcon ConstContractor (applies to all its work) · contractor Dalcon Const
- C7 · High Concurrent Workload for One ContractorRoad Edge Trading & Development ServicesContractor (applies to all its work) · contractor Road Edge Trading & Development Services
- C7 · High Concurrent Workload for One ContractorJwu Const and SupplyContractor (applies to all its work) · contractor Jwu Const and Supply
- C7 · High Concurrent Workload for One ContractorEgb Const Corp Formerly: Egb ConstContractor (applies to all its work) · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure at Brgy. Papan Este, Jones, IsabelaDPWH project · contractor Ma Tesoro Const / Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Barangay Sto. Domingo Flood Control Structure, Section 2, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Linomot Flood Control Structure, Section 2, Jones, IsabelaDPWH project · contractor Dalcon Const
- C4 · Schedule / Date InconsistenciesConstruction of Barangay Papan Weste Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C4 · Schedule / Date InconsistenciesConstruction of Barangay Sto. Domingo Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C4 · Schedule / Date InconsistenciesConstruction of Disimpit Flood Control Structure, Jones, IsabelaDPWH project · contractor Casan Const and Trading
- C2 · Awards Very Close to the Budget CeilingConstruction of Dibuluan Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure, Barangay Ii, Section 2, Jones, IsabelaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Dipangit Flood Control Structure, Section 3, Jones, IsabelaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Arubub Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 730, Jones, IsabelaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Addalam Flood Control Structure, Purok 4, Barangay Addalam, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Bantay Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Jwu Const and Supply
- C2 · Awards Very Close to the Budget CeilingConstruction of Barangay Papan Weste Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Brgy. Panang Flood Control Structure, Sta. 0 + 400 - Sta. 0 + 795, San Agustin, IsabelaDPWH project · contractor Ma Tesoro Const / Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Barangay Sto. Domingo Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Diarao Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Jwu Const and Supply
- C2 · Awards Very Close to the Budget CeilingConstruction of Pongpongan Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Jwu Const and Supply
- C2 · Awards Very Close to the Budget CeilingConstruction of Dipangit Flood Control Structure, Section 2, Jones, IsabelaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Dipangit Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C4 · Schedule / Date InconsistenciesConstruction of Dipangit Flood Control Structure, Section 3, Jones, IsabelaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Papan Weste Flood Control Structure, Section 4, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Linomot Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Dipangit Flood Control Structure, Section 4, Jones, IsabelaDPWH project · contractor Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Struture, Barangay Tupax, Jones, IsabelaDPWH project · contractor Jwu Const and Supply
- C2 · Awards Very Close to the Budget CeilingConstruction of Malannit Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Usol Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Dalcon Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Villa Victoria Flood Control Structure, Brgy. Villa Victoria, Echague, IsabelaDPWH project · contractor Ma Tesoro Const / Egb Const Corp Formerly: Egb Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Dumawing Flood Control Structure, Section 1, Jones, IsabelaDPWH project · contractor Dalcon Const
- C4 · Schedule / Date InconsistenciesConstruction of Santo Domingo Flood Control Structure, Sta. 0 + 226 - Sta. 0 + 553, Santo Domingo, Jones, IsabelaDPWH project · contractor Casan Const and Trading
- C2 · Awards Very Close to the Budget CeilingConstruction of Brgy. Minuri Flood Control Structure, Sta. 0 + 400 - Sta. 0 + 915, Jones, IsabelaDPWH project · contractor Ma Tesoro Const / Egb Const Corp Formerly: Egb Const
- C4 · Schedule / Date InconsistenciesConstruction of Barangay Sto. Domingo Flood Control Structure, Section 2, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Barangay Dibuluan Flood Control Structure, Section 3, Jones, IsabelaDPWH project · contractor V B Manubay Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Barangay Minuri Flood Control Structure, Section 3, Jones, IsabelaDPWH project · contractor V B Manubay Const