13 published flags on records linked to Ilaya and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C1 · Contractor Concentration (Flood Control)Qm BuildersContractor (applies to all its work) · contractor Qm Builders
- C1 · Contractor Concentration (Flood Control)Qm BuildersContractor (applies to all its work) · contractor Qm Builders
- C1 · Contractor Concentration (Flood Control)Centerways Const and Development IncContractor (applies to all its work) · contractor Centerways Const and Development Inc
- C1 · Contractor Concentration (Flood Control)Legacy Const Corp Formerly: Legacy ConstContractor (applies to all its work) · contractor Legacy Const Corp Formerly: Legacy Const
- C1 · Contractor Concentration (Flood Control)Centerways Const and Development IncContractor (applies to all its work) · contractor Centerways Const and Development Inc
- C7 · High Concurrent Workload for One ContractorCenterways Const and Development IncContractor (applies to all its work) · contractor Centerways Const and Development Inc
- C7 · High Concurrent Workload for One ContractorQm BuildersContractor (applies to all its work) · contractor Qm Builders
- C7 · High Concurrent Workload for One ContractorLegacy Const Corp Formerly: Legacy ConstContractor (applies to all its work) · contractor Legacy Const Corp Formerly: Legacy Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Revetment Wall at Barangay Madridejos, Alegria, Cebu (Upstream Left Side)DPWH project · contractor Legacy Const Corp Formerly: Legacy Const
- C4 · Schedule / Date InconsistenciesConstruction of Revetment Wall at Barangay Madridejos, Alegria, Cebu (Upstream Left Side)DPWH project · contractor Legacy Const Corp Formerly: Legacy Const
- C4 · Schedule / Date InconsistenciesConstruction of Revetment Wall, Phase 2, Purok Balanghoy, Barangay Ylaya, Ronda, CebuDPWH project · contractor Rdy Builders Const and Gen Merchandise / Muana Const and Development Corp Formerly
- C4 · Schedule / Date InconsistenciesConstruction of River Retaining Wall Structures Along Ylaya River (Purok Manga Section), Brgy. Ylaya, Ronda, CebuDPWH project · contractor Jcm Ameg Builders Corp Formerly: Ameg Const & Supply
- C4 · Schedule / Date InconsistenciesConstruction of Revetment Wall at Barangay Bala - Barangay Lanao (Upstream Right Side), Moalboal, CebuDPWH project · contractor Sudan Const and Supply Corp
Named parties may reply or request a correction. See the methodology.