BIP: FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BARANGAY TAMAOYAN, LEGAZPI CITY, ALBAY
BIP: FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE SYSTEM ALONG BARANGAY TAMAOYAN, LEGAZPI CITY, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱67,081,389.78. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FIRST OMB CONST AND DEVELOPMENT CORP. Figures trace to dpwh.
Total Contract Cost