Construction of Flood Mitigation Structure22DC0052

Construction of Flood Mitigation Structure along San Juan River, Tanauan - Sto. Tomas, Batangas

Construction of Flood Mitigation Structure along San Juan River, Tanauan - Sto. Tomas, Batangas is a DPWH-tracked public work in CITY OF SANTO TOMAS (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱77,199,364.24. Status: Reported complete (DPWH). Contractor on record: N D M SANCHEZ BUILDERS & DEVELOPMENT CORP. Figures trace to sumbong.

CITY OF SANTO TOMAS (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱29,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Lawaye River, Barangay Palahanan 2.0, San Juan, Batangas
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002895

₱1,037,658,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0010998

₱100,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003021

₱10,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-22-0006164

₱5,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱77,199,364.24

Progress

Reported complete (DPWH)

Start Date

February 23, 2022

Target End

January 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.