Construction of Flood Mitigation Structure23FF0020

Construction of Flood Mitigation Measure along Hibago River, Left Side, Upstream of Hibago Bridge, Brgy. Hibago, Ocampo, Camarines Sur

Construction of Flood Mitigation Measure along Hibago River, Left Side, Upstream of Hibago Bridge, Brgy. Hibago, Ocampo, Camarines Sur is a DPWH-tracked public work in OCAMPO (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱85,981,400.00. Status: Reported complete (DPWH). Contractor on record: PHILWORKS CONST & SUPPLY. Figures trace to sumbong.

OCAMPO (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Rangas River, Brgy. Mampirao, San Jose, Camarines Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Camarines Sur 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱85,981,400.00

Progress

Reported complete (DPWH)

Start Date

February 20, 2023

Target End

December 1, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.