Construction of Flood Mitigation Structure22DF0052

Construction of Flood Control Structure along Manila Bay, Barangay San Rafael IV, Noveleta, Cavite

Construction of Flood Control Structure along Manila Bay, Barangay San Rafael IV, Noveleta, Cavite is a DPWH-tracked public work in NOVELETA (CAVITE), CAVITE, Region IV-A. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: JAGONBUILD CONST CORP FOR JAGON BUILDERS. Figures trace to sumbong.

NOVELETA (CAVITE), CAVITE, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Manila Bay, Barangay San Rafael IV, Noveleta, Cavite
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cavite 1st District Engineering Office · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

January 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.