Flood Control and Drainage23IM0080

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PHASE 2, CAMANSIHAY, TACLOBAN CITY, LEYTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PHASE 2, CAMANSIHAY, TACLOBAN CITY, LEYTE is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱110,573,419.00. Status: Reported complete (DPWH). Contractor on record: LEDA CONST INC 12229. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay 103, Palanog, Tacloban City, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Tacloban City DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 12229

162 projects · ₱8.1B total · 0 flags

4. Implementation

Contract Amount

₱110,573,419.00

Progress

Reported complete (DPWH)

Start Date

June 19, 2023

Target End

May 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.