Construction of Flood Mitigation Structure22OB0026

Improvement of Maytunas Creek, Mandaluyong City (Phase 1)

Improvement of Maytunas Creek, Mandaluyong City (Phase 1) is a DPWH-tracked public work in CITY OF MANDALUYONG (METROPOLITAN MANILA), MANDALUYONG CITY, National Capital Region. Reported contract value: ₱42,808,974.20. Status: Reported complete (DPWH). Contractor on record: DAHL CONST CORP FORMERLY: DAHL CONST. Figures trace to sumbong.

CITY OF MANDALUYONG (METROPOLITAN MANILA), MANDALUYONG CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Banks of Creeks along Shelterville Creek, Brgy. 171 (Phase 2), Caloocan City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001726

₱202,063,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003018

₱90,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001634

₱15,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0001871

₱7,396,262.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003117

₱2,297,896,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0003214

₱1,360,967.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0001872

₱687,910.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0009694

₱529,085.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0003215

₱124,316.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0005641

₱3,168,112.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱42,808,974.20

Progress

Reported complete (DPWH)

Start Date

February 8, 2022

Target End

August 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.