Construction of Flood Mitigation Structure24GG0054

Construction of Flood Control along Jalaur River in Calinog, Iloilo

Construction of Flood Control along Jalaur River in Calinog, Iloilo is a DPWH-tracked public work in CALINOG (ILOILO), ILOILO, Region VI. Reported contract value: ₱34,299,949.95. Status: Reported complete (DPWH). Contractor on record: STRONGLANE BUILDERS AND TRADING CORP FORMERLY: STRONGLANE CONST & TRADING. Figures trace to sumbong.

CALINOG (ILOILO), ILOILO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Jalaur River in Calinog, Iloilo
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0004974

₱15,000,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007676

₱1,767,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0000252

₱315,794.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVI-24-0007677

₱163,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱34,299,949.95

Progress

Reported complete (DPWH)

Start Date

February 12, 2024

Target End

August 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.