Construction of Flood Mitigation Structure23F00025

Construction of Revetment along Quinale River, Downstream of Comun Bridge, Left Side, Barangay Ogob, Malinao, Albay

Construction of Revetment along Quinale River, Downstream of Comun Bridge, Left Side, Barangay Ogob, Malinao, Albay is a DPWH-tracked public work in MALINAO (ALBAY), ALBAY, Region V. Reported contract value: ₱101,324,139.60. Status: Reported complete (DPWH). Contractor on record: MAKAPA CORP. Figures trace to sumbong.

MALINAO (ALBAY), ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System along Lacag-Inarado River, Daraga, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Albay 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

123 projects · ₱9.7B total · 0 flags

Other projects by this contractor

No sat.

OO2-PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION/REHABILITATION OF NASISI RIVER FLOOD MITIGATION STRUCTURE(BRGY. CAVASI AND BRGY. TOMOL

Region V, Region V

2022₱192.9M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS:CONST./IMPV'T. OF CADAC-AN RIVER FLOOD CONTROL SYSTEM,JUBAN, SORSOGON

Region V, Region V

2018₱185.2M
Reported complete (DPWH)

Construction/Improvement/Rehabilitation of Cadac-an River Flood Mitigation Structure, Sta. 12+260 - Sta. 12+308 Right Side, Sta. 11+792 - Sta. 12+848 Left Side, Juban, Sorsogon

JUBAN (SORSOGON), SORSOGON, Region V

2022₱174.7M
Reported complete (DPWH)

Construction/Improvement/Rehabilitation of Cadac-an River Flood Mitigation Structure, Sta. 23+752.00 - Sta. 24+575.57 Left Side, Sta. 23+806.50 - Sta. 24+357.50 Right Side, Irosin, Sorsogon

IROSIN (SORSOGON), SORSOGON, Region V

2022₱174.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NABONTON RIVER, LIGAO CITY, ALBAY

Region V, Region V

2025₱173.6M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS:CONST.OF FLOOD MITIGATION STRUCTURES ALONG SAN AGUSTIN RIVER,LIBON AL

Region V, Region V

2018₱171.0M
Reported complete (DPWH)
View all 123 projects →

4. Implementation

Contract Amount

₱101,324,139.60

Progress

Reported complete (DPWH)

Start Date

March 30, 2023

Target End

February 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.