Construction of Flood Mitigation Structure23CE0124

Construction of Flood Control Structures Along Dibolo Creek, Brgy. Del Pilar, Rizal, Nueva Ecija

Construction of Flood Control Structures Along Dibolo Creek, Brgy. Del Pilar, Rizal, Nueva Ecija is a DPWH-tracked public work in RIZAL (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱98,993,408.99. Status: Reported complete (DPWH). Contractor on record: SPECO BUILDERS INC FORMERLY VRF CONST. Figures trace to sumbong.

RIZAL (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Casongsong River, Brgy. Casongsong, Guimba, Nueva Ecija
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0024916

₱371,572.00 · FY2023

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱98,993,408.99

Progress

Reported complete (DPWH)

Start Date

April 13, 2023

Target End

January 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.