Construction of Flood Mitigation Structure22IJ0051

Construction of Flood Control Structure along Barruz River, Brgy. Barruz, Matuguinao, Samar

Construction of Flood Control Structure along Barruz River, Brgy. Barruz, Matuguinao, Samar is a DPWH-tracked public work in MATUGUINAO (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIII. Reported contract value: ₱48,876,644.33. Status: Reported complete (DPWH). Contractor on record: JFR CONST INC FORMERLY:JFR CONST. Figures trace to sumbong.

MATUGUINAO (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Barruz River, Brgy. Barruz, Matuguinao, Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003145

₱185,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

307 projects · ₱6.1B total · 9 flags

4. Implementation

Contract Amount

₱48,876,644.33

Progress

Reported complete (DPWH)

Start Date

February 8, 2022

Target End

April 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.