Flood Control and Drainage18DN0080

RIPRAPPING OF TAMENGGO CREEK, SITIO LA UNICA, BRGY. CUPANG, ANTIPOLO CITY

RIPRAPPING OF TAMENGGO CREEK, SITIO LA UNICA, BRGY. CUPANG, ANTIPOLO CITY is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱4,704,752.53. Status: Reported complete (DPWH). Contractor on record: EL-JAKE BUILDERS. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱10,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-E-18-0015878 · ₱500,000 · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18DN0080 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-06-07 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Rizal

Based on the coordinates published with the DPWH record and NOAH file Rizal.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: RIPRAPPING OF TAMENGGO CREEK, SITIO LA UNICA, BRGY. CUPANG, ANTIPOLO CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation with Slope protection of Creek, Sitio Dela Paz, Brgy. Cupang, Antipolo City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0015878

₱500,000.00 · FY2018

Released to Rizal 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

117 projects · ₱1.9B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONST/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMSCONST OF FLOOD CONTROL STRUCTURE ALONG KALERO RIVER, BRGY. SAN RAFAEL, NOVELETA, CAV

Cavite 1st DEO, Region IV-A

2024₱100.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG YLANG-YLANG RIVER, BARANGAY SANTA ISABEL,KAWIT

Cavite 1st DEO, Region IV-A

2024₱95.5M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF MULTI-PURPOSE BUILDING WITHIN ZONE 58 TO 67, MANILA CITY (PHASE III)

North Manila DEO, National Capital Region

2025₱78.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN TO BOSO-BOSO RIVER (DOWNSTREAM PHASE 2), K0035+900 ALONG MARIKINA-INFANTA ROAD ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2020₱55.0M
Reported complete (DPWH)
No sat.

IMPROVEMENT/CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN RIVER (UPSTREAM PHASE 7), K0035+900 ALONG MARIKINA-INFANTA ROAD, ANTIPOLO CITY (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2019₱55.0M
Reported complete (DPWH)
No sat.

Construction of Flood Control and Slope Protection Structure along Upper Marikina River, Barangay San Jose, Rodriguez, Rizal

MONTALBAN (RIZAL), RIZAL, Region IV-A

2023₱48.2M
Reported complete (DPWH)
View all 117 projects →

4. Implementation

Contract Amount

₱4,704,752.53

Progress

Reported complete (DPWH)

Start Date

March 5, 2018

Target End

July 2, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)RizalCity of AntipoloCupang
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Man-Yi 2024Trami 2024
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.