Flood Control and Drainage19HD0028

CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT BARANGAY TAPILON, DAANBANTAYAN, CEBU

CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT BARANGAY TAPILON, DAANBANTAYAN, CEBU is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱14,027,719.99. Status: Reported complete (DPWH). Contractor on record: BANTAY CONST. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROX-19-0007996

₱11,641,000.00 · FY2019

Released to Batangas 4th District Engineering Offi Division of El Salvador City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

119 projects · ₱682.0M total · 0 flags

4. Implementation

Contract Amount

₱14,027,719.99

Progress

Reported complete (DPWH)

Start Date

June 24, 2019

Target End

October 24, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.