Flood Control and Drainage24CC0151

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AND WATERWAYS ALONG BOCAUE RIVER, BARANGAY BAMBANG (KAKULISAN), BOCAUE, BULACAN

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AND WATERWAYS ALONG BOCAUE RIVER, BARANGAY BAMBANG (KAKULISAN), BOCAUE, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱98,999,736.58. Status: Past target date (DPWH On-Going). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Waterways and Flood Control Structure along Guiguinto River, Brgy. Malis, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

241 projects · ₱13.6B total · 65 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱98,999,736.58

Progress

Past target date (DPWH On-Going)

Start Date

April 23, 2024

Target End

January 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.