GAA 2025 OO-225IJ0010

OO2: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BARRUZ, PHASE II, MATUGUINAO, SAMAR

OO2: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BARRUZ, PHASE II, MATUGUINAO, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱67,509,097.97. Status: Past target date (DPWH On-Going). Contractor on record: JUPA CONST. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Gandara River, Phase II, Barangay Tawiran, Gandara, Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Samar 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

117 projects · ₱4.4B total · 2 flags

4. Implementation

Contract Amount

₱67,509,097.97

Progress

Past target date (DPWH On-Going)

Start Date

March 25, 2025

Target End

February 12, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.