Construction of Flood Mitigation Structure23IC0038

Construction of Flood Control Structure along Bangon River, Brgy. Arado, Palo, Leyte

Construction of Flood Control Structure along Bangon River, Brgy. Arado, Palo, Leyte is a DPWH-tracked public work in PALO (LEYTE), LEYTE, Region VIII. Reported contract value: ₱48,509,603.99. Status: Reported complete (DPWH). Contractor on record: JGO BUILDERS. Figures trace to sumbong.

PALO (LEYTE), LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bangon River, Brgy. Arado, Palo, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Leyte 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,509,603.99

Progress

Reported complete (DPWH)

Start Date

March 24, 2023

Target End

October 9, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.