Flood Control and Drainage18OC0090

UPGRADING AND DRAINAGE IMPROVEMENT OF J. P. RIZAL AVENUE INCLUDING LATERALS, BRGY. POBLACION, MAKATI CITY, METRO MANILA

UPGRADING AND DRAINAGE IMPROVEMENT OF J. P. RIZAL AVENUE INCLUDING LATERALS, BRGY. POBLACION, MAKATI CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱18,424,208.92. Status: Reported complete (DPWH). Contractor on record: EL-JAKE BUILDERS 38162. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 38162

110 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONST/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMSCONST OF FLOOD CONTROL STRUCTURE ALONG KALERO RIVER, BRGY. SAN RAFAEL, NOVELETA, CAV

Cavite 1st DEO, Region IV-A

2024₱100.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAMCONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG YLANG-YLANG RIVER, BARANGAY SANTA ISABEL,KAWIT

Cavite 1st DEO, Region IV-A

2024₱95.5M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF MULTI-PURPOSE BUILDING WITHIN ZONE 58 TO 67, MANILA CITY (PHASE III)

North Manila DEO, National Capital Region

2025₱78.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN TO BOSO-BOSO RIVER (DOWNSTREAM PHASE 2), K0035+900 ALONG MARIKINA-INFANTA ROAD ANTIPOLO CITY, RIZAL (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2020₱55.0M
Reported complete (DPWH)
No sat.

IMPROVEMENT/CONSTRUCTION OF FLOOD CONTROL STRUCTURES, SITIO KAPATAGAN RIVER (UPSTREAM PHASE 7), K0035+900 ALONG MARIKINA-INFANTA ROAD, ANTIPOLO CITY (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2019₱55.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURES OF BANABA CREEK GOING TO PEACE VILLAGE ES, BRGY. SAN LUIS ANTIPOLO CITY (SECOND DISTRICT)

Rizal 1st DEO, Region IV-A

2020₱47.3M
Reported complete (DPWH)
View all 110 projects →

4. Implementation

Contract Amount

₱18,424,208.92

Progress

Reported complete (DPWH)

Start Date

April 23, 2018

Target End

October 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.