Construction of Flood Mitigation Structure21EH0080

Construction of Shore Protection/Causeway leading to Poctoy Port, Odiongan, Romblon

Construction of Shore Protection/Causeway leading to Poctoy Port, Odiongan, Romblon is a DPWH-tracked public work in ROMBLON, Region IV-B. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: ROLCO CONST & DEVELOPMENT CORP FOR. Figures trace to sumbong.

ROMBLON, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱2,820,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Panique (Upstream) Flood Control, Odiongan, Romblon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014133

₱60,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008602

₱30,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010178

₱2,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

August 6, 2021

Target End

June 14, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.