Flood Control and Drainage25CC0112

CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY CULIANIN (PUROK 4), PLARIDEL, BULACAN

CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY CULIANIN (PUROK 4), PLARIDEL, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱74,111,594.71. Status: Past target date (DPWH On-Going). Contractor on record: TOPNOTCH CATALYST BUILDERS INC. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱50,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25CC0112 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    0% reported · imagery 2018-02-25 → 2025-04-20

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Bulacan

Based on the coordinates published with the DPWH record and NOAH file Bulacan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY CULIANIN (PUROK 4), PLARIDEL, BULACAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay Culianin to Barangay Cambaog, Bustos, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

241 projects · ₱13.6B total · 65 flags

Other projects by this contractor

View all 241 projects →

4. Implementation

Contract Amount

₱74,111,594.71

Progress

Past target date (DPWH On-Going)

Start Date

February 25, 2025

Target End

November 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)BulacanPlaridelCulianin
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Matmo 2025Kajiki 2025Man-Yi 2024
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.