Construction of Flood Mitigation Structure22GG0093

Construction of Flood Control Structure along Jalaur River, Pototan, Iloilo

Construction of Flood Control Structure along Jalaur River, Pototan, Iloilo is a DPWH-tracked public work in POTOTAN (ILOILO), ILOILO, Region VI. Reported contract value: ₱43,217,768.99. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST & SUPPLY INC FORMERLY: ADP CONST & SUPPLY. Figures trace to sumbong.

POTOTAN (ILOILO), ILOILO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Jalaur River, Pototan, Iloilo
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002721

₱676,942,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVI-22-0007458

₱120,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002801

₱94,268,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱43,217,768.99

Progress

Reported complete (DPWH)

Start Date

March 29, 2022

Target End

September 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.