Flood Control and Drainage25EH0034

CONSTRUCTION OF PILI FLOOD CONTROL STRUCTURE PHASE 2, BARANGAY PILI, SAN FERNANDO, ROMBLON

CONSTRUCTION OF PILI FLOOD CONTROL STRUCTURE PHASE 2, BARANGAY PILI, SAN FERNANDO, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱141,048,958.41. Status: Past target date (DPWH On-Going). Contractor on record: SCATR CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱28,101,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Campalingo Flood Control Structure along Sibuyan Circumferential Road, Phase 2, Barangay Campalingo, San Fernando, Romblon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-25-0013588

₱151,000.00 · FY2025

Released to Dr. Santiago Dakudao, Sr. National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱141,048,958.41

Progress

Past target date (DPWH On-Going)

Start Date

March 24, 2025

Target End

March 19, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.