Published flags in Nueva Ecija
87 published flags on records linked to Nueva Ecija and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Baket-Baket River, Package C, Moncada, TarlacDPWH project · contractor T2b3 Builders and Supplies Corp
- C2 · Awards Very Close to the Budget CeilingRehabilitation of Flood Control Structure Along Pampanga River, Brgy. Santa Isabel, Cabiao, Nueva EcijaDPWH project · contractor D B Baraquiel Const / Jerry R Santiago Const Corp Formerly: Jerry Santiago Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Labong River, Brgy. Caingin Tabing Ilog, Guimba, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along PeñAranda River, Barangay San Vicente, Gapan City, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Existing Dike Along Lucung River (Magao Section, Right Bank), Concepcion, TarlacDPWH project · contractor Raik Const and Development Corp Formerly: Raik Const and Supply
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along Pampanga River, Barangay Pagas, Cabanatuan City, Nueva EcijaDPWH project · contractor Celso C Ferrer Const Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure (Gabion) at Pampanga River, Barangay Ligaya, Gabaldon, Nueva EcijaDPWH project · contractor Framecon Builders
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Cassanova Creek, Barangay Nagpandayan, Guimba, Nueva EcijaDPWH project · contractor Ijk Mae Const Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Banco River, Barangay Canaan East, Rizal, Nueva EcijaDPWH project · contractor Irc Const & Supplies / Symmetricon Builders Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Casongsong River, Brgy. Casongsong, Guimba, Nueva EcijaDPWH project · contractor Mivico Builders & Developers
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Rio Chico River, Barangay Macamias, Guimba, Nueva EcijaDPWH project · contractor R D Talens Const and Trading
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Including Road Dike Along PeñAranda River, Barangays San Vicente-San Lorenzo, Gapan City, Nueva EcijaDPWH project · contractor F-Dey Const and Trading / Jerry R Santiago Const Corp Formerly: Jerry Santiago Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structures Along Cassanova Creek, Brgy. Nagpandayan, Guimba, Nueva EcijaDPWH project · contractor Solfio P Jacinto Const Inc / Mivico Builders & Developers
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along PeñAranda River, Barangay Pambuan, Gapan City, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure (Gabion) at Pampanga River, Barangay Ligaya, Gabaldon, Nueva EcijaDPWH project · contractor Framecon Builders
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structures Along Pampanga River, Brgy. Poblacion Norte, Rizal, Nueva EcijaDPWH project · contractor Speco Builders Inc Formerly Vrf Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along Pampanga River, Barangay Pagas, Cabanatuan City, Nueva EcijaDPWH project · contractor Celso C Ferrer Const Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Rio Chico River, Barangay Partida I, Guimba, Nueva EcijaDPWH project · contractor Mivico Builders & Developers
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along PeñAranda River, Barangay Pambuan, Gapan City, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structures Along Casongsong River, Brgy. Casongsong, Guimba, Nueva EcijaDPWH project · contractor R D Talens Const and Trading
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Labong River, Barangay Caingin Tabing Ilog, Guimba, Nueva EcijaDPWH project · contractor Dgsarm Builders Inc Formerly: D G Sarmenta Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Pampanga River, Barangay Poblacion Norte, Rizal, Nueva EcijaDPWH project · contractor Speco Builders Inc Formerly Vrf Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Rio Chico, Barangay Macamias, Guimba, Nueva EcijaDPWH project · contractor NiñAs Const Corp Formerly: Nina'S Const and Supplies
- C3 · Duplicate or Near-Duplicate ProjectsConstruction/Rehabilitation of Flood Control Structures Along Rio Chico River, Brgy. Partida I, Guimba, Nueva EcijaDPWH project · contractor NiñAs Const Corp Formerly: Nina'S Const and Supplies
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Brgy. Palestina, San Jose City, Nueva EcijaDPWH project · contractor Wizard Concrete Solutions and Const Corp Formerly: Wizard Trading & Const
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Existing Dike Along Lucung River (Magao Section, Right Bank), Package F, Concepcion, TarlacDPWH project · contractor Royal Crown Monarch Const & Supplies Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Banco River, Barangay Canaan East, Rizal, Nueva EcijaDPWH project · contractor Irc Const & Supplies / Symmetricon Builders Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Mitigation Structure Along Pampanga River, Sta. 25+760.00-Sta. 26+048.40, Barangay Calaba, San Isidro, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / R G Dela Cruz Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along PeñAranda River, Barangay Santo NiñO, Gapan City, Nueva EcijaDPWH project · contractor Dgsarm Builders Inc Formerly: D G Sarmenta Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Brgy. Sta. Monica, Aliaga, Nueva EcijaDPWH project · contractor R D Talens Const and Trading
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along PeñAranda River, Barangay Sto. NiñO, Gapan City, Nueva EcijaDPWH project · contractor Dgsarm Builders Inc Formerly: D G Sarmenta Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along PeñAranda River, Brgy. San Vicente, Gapan City, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc / N C Aguilar Const & Supply Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Barangay Caridad Norte, Llanera, Nueva EcijaDPWH project · contractor Adroit Ejd Const Corp Formerly: Adroit Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Brgy. Tabulac, San Jose City, Nueva EcijaDPWH project · contractor Ijk Mae Const Inc / NiñAs Const Corp Formerly: Nina'S Const and Supplies
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Dike Along Talavera River, Brgy. San Agustin, Sto. Domingo, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / Kevin Paul Const
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Dike Along Talavera River, Barangay Concepcion to San Agustin, Santo Domingo, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / Kevin Paul Const
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Existing Dike Along Lucung River (Magao Section, Right Bank), Concepcion, TarlacDPWH project · contractor Raik Const and Development Corp Formerly: Raik Const and Supply
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along PeñAranda River, Barangay San Nicolas, Gapan City, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / R G Dela Cruz Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Barangay Palestina, San Jose City, Nueva EcijaDPWH project · contractor Wizard Concrete Solutions and Const Corp Formerly: Wizard Trading & Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Barangay Caridad Norte, Llanera, Nueva EcijaDPWH project · contractor Wizard Concrete Solutions and Const Corp Formerly: Wizard Trading & Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Brgy. Gomez, Llanera, Nueva EcijaDPWH project · contractor Irc Const & Supplies / Symmetricon Builders Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along PeñAranda River, Barangay San Nicolas, Gapan City, Nueva EcijaDPWH project · contractor Itp Const Inc / Pan Aquarius Const and Development Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Rio Chico River, Barangay Macamias, Guimba, Nueva EcijaDPWH project · contractor R D Talens Const and Trading
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structures Along Casongsong River, Brgy. Casongsong, Guimba, Nueva EcijaDPWH project · contractor R D Talens Const and Trading
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Barangay Tabulac, San Jose City, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / Ijk Mae Const Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction/Rehabilitation of Flood Control Structures Along Talavera River, Brgy. Sta. Monica, Aliaga, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure (Gabion) at Pampanga River, Barangay Bugnan, Gabaldon, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure (Gabion) at Pampanga River, Barangay Bugnan, Gabaldon, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Talavera River, Barangay Gomez, Llanera, Nueva EcijaDPWH project · contractor Symmetricon Builders Corp
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Existing Dike Along Lucung River (Magao Section, Right Bank), Package F, Concepcion, TarlacDPWH project · contractor Royal Crown Monarch Const & Supplies Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along Pampanga River, Barangay Calaba, San Isidro, Nueva EcijaDPWH project · contractor Triple S Builders Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure Along PeñAranda River, Barangay San Vicente, Gapan City, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C7 · High Concurrent Workload for One ContractorRoyal Crown Monarch Const & Supplies CorpContractor (applies to all its work) · contractor Royal Crown Monarch Const & Supplies Corp
- C7 · High Concurrent Workload for One ContractorSt Timothy Const CorpContractor (applies to all its work) · contractor St Timothy Const Corp
- C7 · High Concurrent Workload for One ContractorA C Soliven Const & Gen MerchandiseContractor (applies to all its work) · contractor A C Soliven Const & Gen Merchandise
- C7 · High Concurrent Workload for One ContractorNorthern BuildersContractor (applies to all its work) · contractor Northern Builders
- C7 · High Concurrent Workload for One ContractorSt Gerrard Const Gen Contractor & Development Corp Formerly:St Gerrard ConstContractor (applies to all its work) · contractor St Gerrard Const Gen Contractor & Development Corp Formerly:St Gerrard Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Slope Protection Structure, Calinat Dam at Pris Sdc, Science City of MuñOz, Nueva EcijaDPWH project · contractor Ijk Mae Const Inc
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Dike Along Talavera River, Barangay Concepcion to San Agustin, Santo Domingo, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / Kevin Paul Const
- C3 · Duplicate or Near-Duplicate ProjectsRehabilitation of Dike Along Talavera River, Brgy. Concepcion, Sto. Domingo, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Pris Sdc Slope Protection at Calinat Dam, Science City of Munoz, Nueva EcijaDPWH project · contractor Ijk Mae Const Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structures Along Labong River, Brgy. Poblacion Sur, Licab, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / Kevin Paul Const
- C1 · Contractor Concentration (Flood Control)W J P Const and SupplyContractor (applies to all its work) · contractor W J P Const and Supply
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Casongsong River, Brgy. Casongsong, Guimba, Nueva EcijaDPWH project · contractor Mivico Builders & Developers
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Labong River, Barangay Poblacion Sur, Licab, Nueva EcijaDPWH project · contractor Dgsarm Builders Inc Formerly: D G Sarmenta Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction/Rehabilitation of Flood Control Structures Along Rio Chico River, Brgy. Macamias, Guimba, Nueva Ecija (Phase 2)DPWH project · contractor NiñAs Const Corp Formerly: Nina'S Const and Supplies
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Casongsong River, Barangay Casongsong, Guimba, Nueva EcijaDPWH project · contractor Mivico Builders & Developers
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure Along PeñAranda River, Barangay Santo NiñO, Gapan City, Nueva EcijaDPWH project · contractor Dgsarm Builders Inc Formerly: D G Sarmenta Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure Along PeñAranda River, Barangay San Lorenzo, Gapan City, Nueva EcijaDPWH project · contractor F-Dey Const and Trading / Jerry R Santiago Const Corp Formerly: Jerry Santiago Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along Pampanga River, Barangay Sapang Buho, Palayan City, Nueva EcijaDPWH project · contractor Jerry R Santiago Const Corp Formerly: Jerry Santiago Const
- C4 · Schedule / Date InconsistenciesRehabilitation of River Bank Structure Along Pampanga River, Barangay San Pablo, Jaen, Nueva EcijaDPWH project · contractor Nueda Builders Const & Supply Inc
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along PeñAranda River, Barangay Malapit, San Isidro, Nueva EcijaDPWH project · contractor F-Dey Const and Trading
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along PeñAranda River, Barangay Pambuan, Gapan City, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Mitigation Structure Along Pampanga River, Sta. 25+760.00-Sta. 26+048.40, Barangay Calaba, San Isidro, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / R G Dela Cruz Const
- C4 · Schedule / Date InconsistenciesConstruction of Alua Slope Protection Structure Along Pampanga River, Barangay Alua, Phase 2, San Isidro, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C4 · Schedule / Date InconsistenciesRehabilitation of Existing Dike Along Lucung River (Magao Section, Right Bank), Concepcion, TarlacDPWH project · contractor Raik Const and Development Corp Formerly: Raik Const and Supply
- C4 · Schedule / Date InconsistenciesRehabilitation of PeñAranda River Flood Control Structure, Barangay Sinasajan (Right Bank), PeñAranda, Nueva EcijaDPWH project · contractor F-Dey Const and Trading
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along Pampanga River, Palayan City, Nueva EcijaDPWH project · contractor Solfio P Jacinto Const Inc
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along PeñAranda River, Brgy. San Vicente, Gapan City, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc / N C Aguilar Const & Supply Inc
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along PeñAranda River, Barangay San Vicente, Gapan City, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along Pampanga River, Barangay Calaba, San Isidro, Nueva EcijaDPWH project · contractor Triple S Builders Inc
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along Pampanga River, Barangay Pagas, Cabanatuan City, Nueva EcijaDPWH project · contractor Celso C Ferrer Const Corp
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure Along Talavera River, Barangay Caridad Sur, Llanera, Nueva EcijaDPWH project · contractor Speco Builders Inc Formerly Vrf Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure Along PeñAranda River, Barangay Concepcion, General Tinio, Nueva EcijaDPWH project · contractor F-Dey Const and Trading / Jerry R Santiago Const Corp Formerly: Jerry Santiago Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure (Gabion) at Pampanga River, Barangay Ligaya, Gabaldon, Nueva EcijaDPWH project · contractor Framecon Builders
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure Along PeñAranda River, Barangay San Nicolas, Gapan City, Nueva EcijaDPWH project · contractor Amp 723 Const Corp Formerly: A M P Const / R G Dela Cruz Const
- C4 · Schedule / Date InconsistenciesConstruction of PeñAranda River Flood Control Structure, Barangay Santo Tomas, PeñAranda, Nueva EcijaDPWH project · contractor R A Pahati Const & Supply Inc
Named parties may reply or request a correction. See the methodology.