Published flags in Zambales
37 published flags on records linked to Zambales and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C1 · Contractor Concentration (Flood Control)Mindanao RockContractor (applies to all its work) · contractor Mindanao Rock
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Mitigation Structure,Tambak River (Upstream) Phase Iii, Iba, ZambalesDPWH project · contractor Cdc Const & Supplies
- C2 · Awards Very Close to the Budget CeilingConstruction of Slope Protection/Flood Control Structure Along Tambak River (Upstream), Phase 6, Iba, ZambalesDPWH project · contractor Cdc Const & Supplies
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Mitigation Structure, Bayto River (Upstream North Approach), Sta. Cruz, ZambalesDPWH project · contractor Big Bertha Const & Development
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Mitigation Structure,Tambak River (Upstream) Phase Iv, Iba, ZambalesDPWH project · contractor Orani Const and Supply Corp Formerly:Orani Builders & Supply
- C2 · Awards Very Close to the Budget CeilingConstruction of Slope Protection/Flood Control, Brgy. Poonbato, Municipality of Botolan, Province of ZambalesDPWH project · contractor Cdc Const & Supplies
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Mitigation Structure,Tambak River (Upstream), Iba, ZambalesDPWH project · contractor High Strength Dev Corp
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Mitigation Structure,Tambak River (Upstream) Phase Ii, Iba, ZambalesDPWH project · contractor Cdc Const & Supplies
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure at Bucao River North Approach Downstream, Botolan, ZambalesDPWH project · contractor Nicledon Const / Grace Const Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure at Bucao River North Approach Downstream Phase 2, Botolan, ZambalesDPWH project · contractor R A Pahati Const & Supply Inc
- C1 · Contractor Concentration (Flood Control)Hgg Builders & SupplyContractor (applies to all its work) · contractor Hgg Builders & Supply
- C1 · Contractor Concentration (Flood Control)Hgg Builders & SupplyContractor (applies to all its work) · contractor Hgg Builders & Supply
- C1 · Contractor Concentration (Flood Control)Legacy Const Corp Formerly: Legacy ConstContractor (applies to all its work) · contractor Legacy Const Corp Formerly: Legacy Const
- C1 · Contractor Concentration (Flood Control)Alpha & Omega Gen Contractor & Development CorpContractor (applies to all its work) · contractor Alpha & Omega Gen Contractor & Development Corp
- C1 · Contractor Concentration (Flood Control)Alpha & Omega Gen Contractor & Development CorpContractor (applies to all its work) · contractor Alpha & Omega Gen Contractor & Development Corp
- C7 · High Concurrent Workload for One ContractorLegacy Const Corp Formerly: Legacy ConstContractor (applies to all its work) · contractor Legacy Const Corp Formerly: Legacy Const
- C5 · Pattern Consistent with Contract SplittingConstruction of Guisguis Flood Control at Nayum River, Brgy. Guisguis, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C5 · Pattern Consistent with Contract SplittingConstruction of Guinabon Flood Control at Nayum River, Brgy. Guinabon, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C5 · Pattern Consistent with Contract SplittingConstruction of Gama River Slope Protection/ Flood Control Structure Phase 3, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C5 · Pattern Consistent with Contract SplittingConstruction of Gama River Slope Protection/ Flood Control Structure Phase 2, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C7 · High Concurrent Workload for One ContractorSto Cristo Const & Trading Inc for: Sto Cristo Const & TradingContractor (applies to all its work) · contractor Sto Cristo Const & Trading Inc for: Sto Cristo Const & Trading
- C7 · High Concurrent Workload for One ContractorHgg Builders & SupplyContractor (applies to all its work) · contractor Hgg Builders & Supply
- C7 · High Concurrent Workload for One ContractorNorthern BuildersContractor (applies to all its work) · contractor Northern Builders
- C7 · High Concurrent Workload for One ContractorGreat Pacific Builders and Gen Contractor IncContractor (applies to all its work) · contractor Great Pacific Builders and Gen Contractor Inc
- C7 · High Concurrent Workload for One ContractorJtc Cruz Const Co IncContractor (applies to all its work) · contractor Jtc Cruz Const Co Inc
- C7 · High Concurrent Workload for One ContractorAlpha & Omega Gen Contractor & Development CorpContractor (applies to all its work) · contractor Alpha & Omega Gen Contractor & Development Corp
- C7 · High Concurrent Workload for One ContractorRosbill Const and SupplyContractor (applies to all its work) · contractor Rosbill Const and Supply
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure,Tambak River (Upstream) Phase Iv, Iba, ZambalesDPWH project · contractor Orani Const and Supply Corp Formerly:Orani Builders & Supply
- C1 · Contractor Concentration (Flood Control)Sto Cristo Const & Trading Inc for: Sto Cristo Const & TradingContractor (applies to all its work) · contractor Sto Cristo Const & Trading Inc for: Sto Cristo Const & Trading
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Mitigation Structure,Tambak River (Upstream), Iba, ZambalesDPWH project · contractor High Strength Dev Corp
- C1 · Contractor Concentration (Flood Control)Rosbill Const and SupplyContractor (applies to all its work) · contractor Rosbill Const and Supply
- C4 · Schedule / Date InconsistenciesConstruction of Guinabon Flood Control at Nayum River, Brgy. Guinabon, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C4 · Schedule / Date InconsistenciesConstruction of Gama River Slope Protection/ Flood Control Structure Phase 3, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C4 · Schedule / Date InconsistenciesRehabilitation of Pamatawan River Downstream ( Old San Agustin Section), Castillejos, ZambalesDPWH project · contractor Orani Const and Supply Corp Formerly:Orani Builders & Supply
- C4 · Schedule / Date InconsistenciesConstruction of Guisguis Flood Control at Nayum River, Brgy. Guisguis, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C4 · Schedule / Date InconsistenciesConstruction of Gama River Slope Protection/ Flood Control Structure Phase 2, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C4 · Schedule / Date InconsistenciesImprovement of Calapacuan River, Subic, ZambalesDPWH project · contractor Sto Cristo Const & Trading Inc for: Sto Cristo Const & Trading
Named parties may reply or request a correction. See the methodology.