Rehabilitation / Major Repair of Flood Control Structure22FI0003

Rehabilitation/Improvement of Narangasan River Control, Milagros, Masbate

Rehabilitation/Improvement of Narangasan River Control, Milagros, Masbate is a DPWH-tracked public work in MILAGROS (MASBATE), MASBATE, Region V. Reported contract value: ₱25,080,160.00. Status: Reported complete (DPWH). Contractor on record: GACT ENT. Figures trace to sumbong.

MILAGROS (MASBATE), MASBATE, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱50,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVIII-22-0012742 · ₱24,753,000 · release to the district office, not itemized per project

    Possible match · score 0.62

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22FI0003 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-05-12 → 2025-05-10

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Masbate

Based on the coordinates published with the DPWH record and NOAH file Masbate.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Rehabilitation/Improvement of Narangasan River Control, Milagros, Masbate

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Bito River (Downstream), Brgy. Curbada, San Fernando, Masbate
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0012742

₱24,753,000.00 · FY2022

Released to Eastern Visayas Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001632

₱55,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003141

₱17,224,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006794

₱10,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

77 projects · ₱873.4M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD-JUNCTION NATIONAL ROAD TO BARANGAY MANAGANAGA TO BAR

Masbate 2nd DEO, Region V

2023₱49.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF CALASUCHE SEAWALL, MILAGROS, MASBATE

Masbate 2nd DEO, Region V

2024₱49.0M
Reported complete (DPWH)
No sat.

Construction of Flood Control Concrete Revetment at Marcella River, Upstream Leftside, Barangay Marcella, Sta. 0+000.00 - Sta. 0+165.00, Uson, Masbate

USON (MASBATE), MASBATE, Region V

2023₱39.1M
Reported complete (DPWH)
No sat.

Construction of Gaid Flood Control, Sta. 0+796.00 - Sta. 0+937.00, Upstream Left Side, Barangay Gaid, Dimasalang, Masbate

DIMASALANG (MASBATE), MASBATE, Region V

2023₱37.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS SECONDARY ROADS - JCT. TAWAD-BALUD RD. K0065+564 - K0065+800, BALUD, MASBATE

Masbate 2nd DEO, Region V

2023₱32.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - MASBATE - CATAINGAN - PLACER RD. (S00005MT) K0001+627 - K0001+760, K0001+779 - K0001+855, K0008+382 - K0008+723, MASBATE CITY AND MOBO, MASBATE

Masbate 2nd DEO, Region V

2020₱29.7M
Reported complete (DPWH)
View all 77 projects →

4. Implementation

Contract Amount

₱25,080,160.00

Progress

Reported complete (DPWH)

Start Date

February 8, 2022

Target End

August 16, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)MasbateMilagrosCapaculan
Storms whose wind field reached it
Nokaen 2026Koto 2025Fung-Wong 2025Kalmaegi 2025Fengshen 2025
Hazard exposure
Flood (100-yr rain)Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.